What is managing contracts in project management?What is managing contracts in project management?

Definition

A contract is an agreement made between two or more parties that creates legally binding obligations between them.

The contract sets out those obligations and the actions that can be taken if they are not met.

Definition from APM Body of Knowledge 7th edition

Contracts can set expectations between project professionals and suppliers – understanding what contract is being used can prevent issues that hinder project delivery. The relationship between project professionals and contractors must be good, with mutual respect so that projects are successful. Contracts are key in projects and new research in the Dynamic Conditions of Project Success shows that they are conditions that enable project success. Read more about the conditions that improve project outcomes here.

The importance of contracts in project management

Contract management is vital for project managers, and of central importance to most projects. Contracts are covered by contract law. Project managers should always seek specialist advice to ensure that the legal ramifications of any proposed contract are fully understood.

It is the project manager’s responsibility to ensure that certain key principles are followed when selecting and managing contractors and suppliers. For example, using an objective process to select the contractor, avoiding influence of personal preferences; making sure there is understanding of what the contractor wants from the arrangements; and involving the contractor in the project team activities where it’s practical.

Once a contract between project manager and client is agreed and the contract is awarded, project professionals arrange to monitor and manage supplier performance in line with the contract. There are some important controls relevant to all contracts that project professionals should put in place:

  1. Understanding the contract obligations

  2. Planned meetings to review progress and identify issues

  3. Formalised reporting, communication and escalation routes

  4. A route to sharing perceptions of risk and putting into place effective responses

Controls that support contract management
Source: APM Body of Knowledge 7th edition

Various types of contracts in project management:

  • The simplest arrangement contractually is a comprehensive contract in which one supplier is responsible for everything required for a project.
  • A sequential contract is the use of two or more contractors during a project. For example, in the traditional system for public works, one organisation may be employed to design a project and another organisation to construct it. The second contract in such arrangements can be a comprehensive commitment to supply all the goods and remaining services required to complete the project.
  • A parallel contract is where a similar scope of work is given to two or more suppliers and they work in parallel to deliver the complete project. For example, a refurbishment contract for a three-story office block where one contractor does the ground floor, another the first and another the second and so on.
  • A sub-contract is a type of contract where the main contractor has a contract, and then sub-contracts it to others to complete.
  • Partnering or a joint venture is where large projects are completed by a number of suppliers coming together to form a partnership.

There’s a spectrum to the complexity of contracts; the more experience you gain managing projects, the more you’ll come across contracts and procurement, and the more complex they’ll become.

There is a general trend of moving towards mutually beneficial ‘win–win’ contracts, where risk is shared on a pain/gain share basis. Projects work best when there is collaboration between clients and contractors in the supply chain.

A collaborative relationship with your contractor is more likely to maximise resource usage, achieve project deliverables, and manage costs.

Watch: What is contracts management?

This video is hosted by a third party (YouTube.com), you cannot view this video content unless you accept marketing cookies. If the popup doesn't appear, please clear your browser cache and refresh the page.

25 Aug - 🕑 52 mins

THE APM PODCAST

Contracts and collaboration in a post-COVID world

Contracts create legally binding obligations between the parties involved in a project. They describe the nature of those obligations and the actions that can be taken if they are not met. As such, the contract is a foundational document whose content will come to define the project and how the work unfolds. It is there to provide certainty and protection to the parties. But in a post-COVID world, there may be an opportunity for contracts to be used to create ongoing collaborative relationships, rather than simply defining strict requirements and being regarded as a tool to give parties leverage in the event of acrimony.

Explore all podcasts

APM Guide to Contracts and Procurement

APM Guide to Contracts and Procurement: For Project, Programme and Portfolio Managers offers a basic understanding of ‘how to’ procure sub-project works and to manage delivery through the phases of the procurement life cycle.

Buy from bookshop
Contracts

Procuring for agile projects

Agile methodologies developed in the fast-moving IT sector have become popular in the last decade. However, the whole world – not just IT – is moving faster in a more VUCA (volatile, uncertain, complex and ambiguous) environment. Consequently, project delivery
methods are becoming more adaptable and collaborative.

View opinion piece
Procuring

Related reading

Crane 620 X 620[1]
A systems-based approach can improve outsourcing in government projects
To remain responsive to challenges faced within today’s uncertain and complex outsourcing ecosystem, government organisations must innovate and evolve their practices to accommodate change... read more.
Sustainability 620 X 620
Why subcontract management is a cornerstone of project risk management
To manage a project effectively, project risk management is vital. The changing world faces new challenges including climate change, artificial intelligence and technology, and more... read more.
Plane Engine 620 X 620[1]
Procuring for agile: thoughts on what good looks like webinar
Based on a white paper on when and how to procure projects which are towards the agile end of the waterfall-agile spectrum. These approaches have been applied in sectors such as mining, aviation and civil engineering... read more.
Buildings 3 620 X 620[1]
Basic knowledge of contract law is essential for an effective project manager
There are many different considerations for project managers to think about when procuring and managing external project suppliers... read more.
Building 620 X 620[1]
How to procure for agile projects
“We are going to be agile, and we are not going to see cost overruns in delivering this project.” How many times have you heard this statement in your project delivery career?... read more.
urban, infrastructure
Point of law - legal pitfalls and how to handle them
Dr Jon Broome and Rob Horne explain what every project manager needs to know about offer and acceptance, and look at the common legal pitfalls... read more.

Basic Contract Law for Project Managers Part 1

This video is hosted by a third party (YouTube.com), you cannot view this video content unless you accept marketing cookies. If the popup doesn't appear, please clear your browser cache and refresh the page.

Top 10 ways to protect yourself through the contract

This video is hosted by a third party (YouTube.com), you cannot view this video content unless you accept marketing cookies. If the popup doesn't appear, please clear your browser cache and refresh the page.

APM Contracts and Procurement Interest Network

The C&P Interest Network exists to promote and disseminate knowledge, understanding and best practice of contracts and procurement in a project environment. It aims to become a lively and constructive debating forum which takes existing best practice and helps make it better.

Join our community

APM Body of Knowledge 7th edition

The APM Body of Knowledge 7th edition is a foundational resource providing the concepts, functions and activities that make up professional project management. It reflects the developing profession, recognising project-based working at all levels, and across all sectors for influencers, decision makers, project professionals and their teams. 

Buy from the bookshop
A book titled APM Body of Knowledge placed on an office desk

You may also be interested in

Laptop screen showing the APM Learning dashboard
APM Learning

The APM Learning portal is an online resource which provides members with access to digital guides, modules and other digital learning resources as part of the membership benefit.

Man wearing headphones using a tablet whilst sat on the sofa
What is ...?

Browse our popular project management 'What is ...?' topics for definitions, quick insights, view related case studies, research, blogs and glossary.

A magazine spread featuring a vibrant photo of diverse individuals engaging on a lively city street.
Project Journal

Project – APM's official journal – is circulated quarterly for members only, and online for regularly updated news, blogs, opinions and insights for those in the project community.

A woman engaged with her laptop, accessing a website while seated at a desk in a well-lit environment.
APM Community

The APM Community is our online community platform that connects our members faster and easier than ever before.

Our APM Community portal is currently offline. Please check back soon.